To: All Gatwick Airline Operators
1. Introduction
Gatwick Airport Ltd. is planning to carry out a number of developments on and around the Main Runway. These developments will increase the length available for aircraft departing on runway 26L and will also enhance runway capacity.
Following a review to identify
the most effective way of undertaking the work and minimising its impact
on operations, it has been decided that a major part will be undertaken
during the period July to September 1996. At this time of year the weather
conditions are likely to be the most favourable and the effect of the loss
of ILS facilities will be minimal.
2. Outline Programme
From July 1 to September
30, the following will be carried out
· Relocation of 08R
ILS Localiser aerial
· Construction of
158m. starter strip and Rapid Access Taxiway for 26L
· Resurfacing of
Main Runway Touchdown Zones
· Construction of
new 08R Rapid Access Taxiway between Delta and Echo
The Main Runway 26L/08R will
have reduced ILS availability. as follows:
26L - CAT I
08R - Visual
Between 2300-0600 Local Time every night of the week apart from Sundays, the Main Runway will be closed and the Northern Runway 26R/08L in use.
The whole project is due
for completion in the Spring of 1997, but from September onwards the works
will not have any impact on the Main Runway.
3. Further Information
Promulgation of more detailed information will take place through the usual channels nearer to the start date. in the meantime if you have any questions, please contact the undersigned